Commercial Exterior Wall Finish Example
More than 100%
You create a valuation for a building that has two to three feet of exposed foundation where the exterior wall finish is carried down over the foundation.
Example 1: The building itself is 100% brick on masonry. To account for the additional cost of having the brick over the masonry foundation wall, you add an additional 10% to the brick on masonry exterior wall finish for a total of 110%.
Example 2: The building itself is 100% brick on frame. To account for the additional cost of having the brick over the masonry foundation wall, you add 10% to the brick on masonry exterior wall finish for a total of 110%
Less than 100%
You create a valuation for a gymnasium built in a warm climate. To allow for as much natural air movement as possible, 20% of the exterior wall has no finish at all. The bottom four feet of exterior wall finish and the top foot of exterior wall finish has been omitted.
Example: The building itself has metal siding on 80% of the exterior wall that has a finish. Enter 80% siding, metal or other on girts and the system calculates a value based on 80% of the exterior wall having a finish.
For reporting purposes, it is recommended that you also enter 20% none. This will prevent any misconceptions that your valuation is incomplete.